Projects  /  Commercial & signage  /  Atlanta, GA

Reverb by Hard Rock

An 86-foot LED display craned onto the corner of the Reverb by Hard Rock tower in Atlanta

LED videoStructureEngineeringRemoval

The project

LucentHD replaced the LED display that runs up the corner of the Reverb by Hard Rock hotel tower in downtown Atlanta, steps from Mercedes-Benz Stadium. Working from a crane and large boom lifts behind street and sidewalk closures, we removed the old display, provided stamped structural drawings and added new secondary steel to the tower's existing frame. We then craned 28 sections into place to build a 10 mm LED screen about 25 feet wide and 86 feet tall, and finished it with stitch bolting, seam alignment, perimeter trim and a new placard. The display was running content by early June 2026.

What we delivered

  • Stamped structural drawings for mounting the new display on the tower's existing steel frame
  • Removal of the old LED display, then new secondary steel welded to the base of the existing frame
  • 28 LED sections set by crane, forming a 10 mm display about 25 feet wide and 86 feet tall
  • Stitch bolting, pinch plates and seam alignment across the display face
  • Perimeter trim and a new identification placard
  • Street and sidewalk closures, traffic control and right-of-way permits on Mitchell Street
VENUE
Reverb by Hard Rock Atlanta Downtown, 89 Centennial Olympic Park Drive NW
LOCATION
Atlanta, GA
TYPE
Commercial & signage
LUCENTHD SCOPE
LED video, Structure, Engineering, Removal
COMPLETED
2026
Start to finish
The crane lifts one of the last display sections to the top of the tower

ConstructionThe crane lifts one of the last display sections to the top of the tower

The new display on the corner of the Reverb by Hard Rock tower in downtown Atlanta

CompleteThe new display on the corner of the Reverb by Hard Rock tower in downtown Atlanta